Four process flow of converter dust removal ash cold solidification pellets


key word:Direct reduction of iron, electric furnace, drying

Source: internal company


1.Material Preparation


◆Dust removal ash from the converter is transported to the raw material silo and unloaded pneumatically. It is then humidified, mixed, and sent to the digestion bin.
◆Starch dry powder adhesive is stored, chosen for its low Si content and good mixing performance.
◆Oxidized iron sheet is stored for future use.

2.Ingredient Compaction


◆The digested mixture, binder, and iron oxide scale are mixed in a double helix mixer and then sent to the wheel mill for backup.
◆In the wheel mill, materials are thoroughly mixed and compacted.
◆The compacted material is discharged and transported back to the ball roller's intermediate warehouse.



3.Ball Pressing and Sieving


◆The crushed mixture is fed into the ball compactor and pressed into balls. The balls and unformed powder are then transported to a screening station. The powder is recycled for further pressing, while the qualified balls proceed to the drying equipment.

4.Drying and Final Sieving


◆Raw balls are dried in a vertical drying bin and then quantitatively discharged for secondary screening. The screened material is either recycled or loaded for transportation.

■The Development and Practical Role of Pure Hydrogen Metallurgy

■Application of Direct Reduced Iron in Electric Furnaces

■Roll skin wear of ball press machine

■The impact of bentonite on pellet production in China

■5 Factors Affecting Energy Consumption of Electric Arc Furnace Steelmaking



Where there is briquette, mixing, drying,
and related system solution,there is Kaizheng








Copyright@2024 Luoyang Kaizheng Environmental Protection Processing Equipment Co., Ltd